Decision Made Parks & Rec Public Works District 4

Neighborhood Park Accessibility Upgrades

Three neighborhood parks will receive accessible paths, play features, restrooms, seating, and sensory-friendly improvements.

Neighborhood Park Accessibility Upgrades project area and community engagement concept.
Project notice: Decision Made The approved concept plans will move into construction documents and a combined public bid package.
View the latest project updates

Project overview

Three neighborhood parks will receive accessible paths, play features, restrooms, seating, and sensory-friendly improvements.

What this project delivers

  • Continuous accessible routes to every major park feature.
  • Inclusive play equipment and sensory-friendly spaces.
  • Accessible picnic areas, restrooms, seating, and drinking fountains.

Community involvement

Families, disability organizations, nearby schools, and older adults tested concepts and prioritized improvements at each park.

Community members want decisions documented clearly and engagement to continue after construction or adoption.

Community engagement summary

What happens next

The approved concept plans will move into construction documents and a combined public bid package.

Project team

Parks & Recreation leads the work with Procurement, Communications, operations staff, and community partners.

Project timeline

Updated July 17, 2026

  1. Discovery and scope

    May 19, 2025 – December 21, 2025

    Discovery and scope for Neighborhood Park Accessibility Upgrades, including documented decisions and public updates.

  2. Community review

    December 21, 2025 – July 26, 2026

    Community review for Neighborhood Park Accessibility Upgrades, including documented decisions and public updates.

  3. Design and approvals

    July 26, 2026 – February 27, 2027

    Design and approvals for Neighborhood Park Accessibility Upgrades, including documented decisions and public updates.

    Current phase · 20% complete
  4. Delivery and closeout

    February 27, 2027 – October 1, 2027

    Delivery and closeout for Neighborhood Park Accessibility Upgrades, including documented decisions and public updates.

Latest updates

View all updates