All projects

District 5

Planning
  • Public Safety
  • District 5
  • $18.6 million

A resilient emergency operations center is being planned to coordinate multi-agency response during severe weather, wildfire, outages, and other emergencies.

Project progress22% complete

ScheduleApril 6, 2026to September 30, 2029

In Progress
  • Housing
  • District 5
  • $16.3 million

A new neighborhood recreation center will provide affordable fitness, aquatics, youth programs, community rooms, and outdoor gathering space.

Project progress61% complete

ScheduleMarch 24, 2025to July 31, 2027

In Progress
  • Public Works
  • District 5
  • $9.6 million

Aging water mains are being replaced to improve reliability, fire flow, and water quality while coordinating street restoration in the South Avenue area.

Project progress41% complete

ScheduleNovember 3, 2025to August 15, 2027